Key incentives for stakeholders |
- Deemed extension of PPA period to projects achieving early commissioning
- A one-time grant of Rs. 25 Lakh/substation from Green Cess Fund
- Land lease @ Rs. 1,25,000/Ha with 3% escalation for private landowners and farmer
- Rs. 5 Lakh/year to the Gram panchayat for 3 years
- Rs. 0.25/kWh for injection @ 11 kV and Rs. 0.15/kWh for injection @ 33 kV
- Seasonally indexed deemed generation @ 100% of appliable tariff
- Provision of common evacuation line for multiple projects
|
Innovative transaction structure designs |
- SPV for Revenue land
- Grouping of private and Revenue land
- Back-to-back lease-sublease; PPA –PSA arrangement
- Dedicated nodal agency for the program
|
Measures for de-risking |
- Data room housing GIS layered land details
- Single window clearance mechanism
- Bottom up, consumption-based project sizing in alignment with KUSUM - C
- Tagging projects with KUSUM - C to avail CFA
- Payment security via revolving fund, LC
|