To supply electricity to the farmers during the day time by installing ground mounted decentralized solar power projects.
Increase in Farmers income by utilizing their barren and uncultivable land for solar plants.
Decentralized Solar Projects:
Required Capacity: 0.5 MW to 2 MW
Required land : Minimum 3 Acres to Maximum 10 Acres
Required distance from MSEDCL Substation : Maximum 5 Km
Connectivity: 11KV /22 KV bus bar of MSEDCL 33/22/11 KV substation.
Tender features:
Who can participate?
Individual farmer, Co-operatives, Panchayat’s, Farmer Producers Organization (FPO), Water Users Association (WUA), Solar Power Generator (SPG).
If unable to arrange sufficient equity Farmers/Cooperatives/ Panchayats / FPO / WUA can opt for developing the project through developer(s) by providing land on lease basis. Monthly lease rent payment will be deducted from the Invoice of energy bill generated by Solar Power Generator (SPG) and paid directly to the farmers by MSEDCL.
Bidder’s Scope: Land development, Solar Infrastructure works, Power Evacuation, Grid Connectivity, Topographical Survey, approach road, all clearances from state government & Local bodies.
Bidder Eligibility criteria:
Net Worth - INR 1 Cr per MW annually.
Turn Over- INR 25 lakhs per MW annually.
PPA tenure: 25 Years
Commissioning: 12 Months from date of issue of LOA